Getting More Out of School Construction Dollars

By Octavio J. Visiedo — January 22, 1997 3 min read
  • Save to favorites
  • Print

As schools across America burst at the seams with the added enrollment of the so-called baby-boom echo, state and municipal taxpayers are being saddled with growing costs for building new facilities. In some cities, enrollment growth is so rapid that officials can’t build schools fast enough.

But in fast-growing Miami, Fla., public school administrators have cut both time and costs through a construction method known as “design/build.” Common in such industries as transportation and defense, design/build is less widely used in education. But that is starting to change, as states begin easing regulations that have long limited school officials’ options.

Take Miami, for example. Until 1986, Florida law required school districts to hire separate contractors for the design and for the construction of public schools. An architect would draw up plans, then hand them off to a builder. The builder would then construct the school under the supervision of school administrators or an outside management firm. During construction, the builder inevitably would discover the need to vary from the plans, prompting costly change orders and construction delays.

But now, a district such as Miami’s Dade County schools may hire one contractor for both jobs. As the Dade County, Fla., superintendent from 1990 until last June--and before that, as the deputy superintendent in charge of the district’s billion-dollar school construction program--I saw firsthand the savings that design/build delivers.

The first school we built under this arrangement was G. Holmes Braddock Senior High, now Florida’s largest school, at 39,356 square feet. Since that initial success, the Florida legislature has refined its 1986 design/build statute, making it easier for school officials to hire contractors according to design/build standards and to favor those firms with the most design/build expertise and experience. With the refinements in place, Dade County has turned to design/build as its preferred approach. The result: $3.6 million in savings since 1995.

Compare two Dade schools opened last fall. The facilities’ specifications were similar. The only significant difference: Wesley Matthews Elementary was designed and built the traditional way, while John I. Smith was design/built instead.

The Matthews project was begun in February 1993, nearly a year and a half before the Smith project; yet Smith, the design/build school, was finished and occupied three weeks before the traditionally built Matthews.

Total delivery time for the traditional school: three years, eight months, and three weeks.

Total delivery time for the design/build school: two years and two months.

In severely overcrowded Dade County, every design and construction day counts. Thanks to design/build, Smith Elementary students were spared more than a year and a half in cramped classrooms. No price can approximate the worth in terms of their education.

But the savings can be calculated in dollars, and they’re significant. Here again, design/build--not to mention the Dade County district--comes out ahead.

The total cost to design and build Matthews: $11,166,633.

The total cost to design/build Smith: $10,729,436.

That’s a savings of $437,197, not including interest earned.

Where do the time and money savings come from? Better communication and better management inherent to the design/build process, according to the Jacksonville-based firm that delivered Smith. With design/build, there’s no communication gap between the designers and the builders because they’re one and the same, and they work together every step of the way. The project price is guaranteed at the start, and the only change orders are those requested by the owner.

As with every innovation, design/build has its detractors. This was originally so within my administration in Dade County and among some legislators and educators around Florida. Unproven in the education arena, they said. Not enough attention to aesthetics.

But Dade’s mounting track record belies those concerns, as does the beauty of Dade’s John I. Smith Elementary School and of Broward County, Fla.'s award-winning New River Middle School, both design/built by the same company.

The approach may not be for every project or for every school district. But for booming districts looking for quick, efficient delivery at less cost, design/build may well be the answer. For Dade County, it’s been a godsend. The proof’s in the numbers--and in the education of our students.

The not-for-profit Design/Build Institute of America recently published a “manual of practice” with technical and procedural information. To obtain a copy, call or write the institute at 1010 Massachusetts Ave. N.W., Suite 350, Washington, D.C. 20001; (202) 682-0110.

In March 2024, Education Week announced the end of the Quality Counts report after 25 years of serving as a comprehensive K-12 education scorecard. In response to new challenges and a shifting landscape, we are refocusing our efforts on research and analysis to better serve the K-12 community. For more information, please go here for the full context or learn more about the EdWeek Research Center.

A version of this article appeared in the January 22, 1997 edition of Education Week

Events

Artificial Intelligence K-12 Essentials Forum Big AI Questions for Schools. How They Should Respond 
Join this free virtual event to unpack some of the big questions around the use of AI in K-12 education.
This content is provided by our sponsor. It is not written by and does not necessarily reflect the views of Education Week's editorial staff.
Sponsor
School & District Management Webinar
Harnessing AI to Address Chronic Absenteeism in Schools
Learn how AI can help your district improve student attendance and boost academic outcomes.
Content provided by Panorama Education
This content is provided by our sponsor. It is not written by and does not necessarily reflect the views of Education Week's editorial staff.
Sponsor
Science Webinar
Spark Minds, Reignite Students & Teachers: STEM’s Role in Supporting Presence and Engagement
Is your district struggling with chronic absenteeism? Discover how STEM can reignite students' and teachers' passion for learning.
Content provided by Project Lead The Way

EdWeek Top School Jobs

Teacher Jobs
Search over ten thousand teaching jobs nationwide — elementary, middle, high school and more.
View Jobs
Principal Jobs
Find hundreds of jobs for principals, assistant principals, and other school leadership roles.
View Jobs
Administrator Jobs
Over a thousand district-level jobs: superintendents, directors, more.
View Jobs
Support Staff Jobs
Search thousands of jobs, from paraprofessionals to counselors and more.
View Jobs

Read Next

Education The Education Word of 2024 Is ...
Educators, policymakers, and parents all zeroed in on students' tech use in 2024, which prompted this year's winner.
5 min read
Image of a cellphone ban, disruption, and symbol of AI.
Laura Baker/Education Week via Canva
Education Opinion The Top 10 Most-Read Opinions on Education of 2024
Look back at what resonated with readers the most this year.
1 min read
Collage illustration of megaphone and numbers 1 through 10.
Education Week + Getty
Education Quiz Education Week News Quiz: Dec. 12, 2024
Test your knowledge on the latest news and trends in education.
1 min read
Sets of hands holding phones. Scrolling smartphones, apps mail, applications, photos. cellphone camera.
Vanessa Solis/Education Week + iStock/Getty Images
Education Quiz Education Week News Quiz: Dec. 5, 2024
Test your knowledge on the latest news and trends in education.
1 min read
President Donald Trump listens during a "National Dialogue on Safely Reopening America's Schools," event in the East Room of the White House, on July 7, 2020, in Washington.
President Donald Trump listens during a "National Dialogue on Safely Reopening America's Schools," event in the East Room of the White House, on July 7, 2020, in Washington.
Alex Brandon/AP